Membrane work, June 23, 2026

Weather: 32°C, sunny
Workers onsite: 2

Work done today:

  • Additional pavers for the sidewalk added to the emergency repair area.
  • Some metal flashing (trim) has been restored to some patios.
  • Patio railings were re-instated (see photos and notes on this below).

Building 244 entrance closure Thursday, June 25, 2026 (both notices)

Today, Quay Pacific prematurely sent out a notice regarding the temporary closure of the 244 building entrance. A short time later, a revised notice was sent out. I will be providing both notices below.

Also unlike Prostar, I’ll include a map of the entrances and exits of the 244 building.

Here’s the revised notice:

And here’s the original notice:

Here is a map showing the exits and entrances to the 244 building.

With the main entrance closed, you can exit and enter the 244 building as follows:

  • Exit only: Through the fire door immediately to the left of the main entrance. No key or fob required.
  • Exit only: Through the fire door at the east end of the hallway on the first floor. No key or fob required.
  • Exit and entrance: Through the door to the left of the underground parking entrance. This requires a fob for entry into the building, same as the main entrance.

Membrane work, June 22, 2026

Weather: 32°C, sunny
Workers onsite: At least 4

Work done today:

  • River stone/gravel was added to some of the emergency repair area.
  • Additional pavers/pedestals were placed on some patios.
  • Pavers were extended in the Phase 1 extension area in a way that doesn’t match the previous design–see photos below.

Membrane work, June 20, 2026

Weather: 23°C, sunny
Workers onsite: At least 4

Work done today:

  • Work today was focused on restoring pavers on patios in the emergency area. This work is nearly complete.

Membrane work, June 19, 2026

Weather: 26°C, sunny
Workers onsite: At least 4-6

Work done today:

  • Sidewalk pavers re-instated in emergency repair area.
  • Many of the pavers on patios in the emergency area have been re-instated, with pedestals being used in place of what were previously wooden beams.
  • Some initial re-instatement of the parking lot pavers along the sidewalk in the Phase 1 extension.

Membrane work, June 18, 2026

Weather: 27°C, sunny
Workers onsite: At least 6

Work done today:

  • Sand and soil are being placed in the emergency repair area.
  • Some patio pavers have been put back in place in the same area.