Phase 2 membrane project, Day 20–August 12, 2026

Weather: 27°C, sunny
Workers onsite: At least five

Work done today:

  • Most of the remaining concrete slab of Stage 3 stripped and polished
  • Sealant applied to most of the same area (see photo below for exception)
  • Additional restoration of pavers to some patios

In the photo above, you can where work was done to cut pavers. This requires the use of tools that use water to prevent overheating from the blade. The water flowed down onto the concrete slab (direction indicated by white arrow) and into the area circled in red, preventing them from finishing applying the sealant, as the area must be clean and dry. The circled area shows exposed concrete slab, with sealant to the left and membrane (previously applied) to the right. Why the workers chose to cut pavers so close to an active work area–which then compromised the work area–is a question left to the reader.

Phase 2 membrane project, Day 19–August 11, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 26°C, sunny
Workers onsite: At least five

Work done today:

  • Pavers put back or partially restored on four patios
  • Membrane completed on four of the five Building 240 patios
  • Initial clearing of the last area on the south side of the parking lot, to allow for removal of old membrane

Phase 2 membrane project, Day 18–August 10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, sunny
Workers onsite: At least two

Work done today:

  • Additional work on patios by the 240 and 244 buildings

Phase 2 membrane project, Day 17–August 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, sunny
Workers onsite: At least two

Work done today:

  • Additional work on the patios around the 240 and 244 buildings