Phase 1 Membrane Project, Day 3 (August 13, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

I observed someone working on and in the C container, but no further work on the property was done today that I could see.

Phase 1 Membrane Project, Day 2 (August 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Day 2 saw actual work begin:

  • The C container arrived and was set up on the central courtyard
  • A subcontractor to Prostar began and completed most of the sod removal behind and along the south side of the 244 building

Phase 1 Membrane Project, Day 1 (August 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Day 1: August 11, 2025

This was mobilization day, devoted mainly to some setup and a look at the site. Work today included:

  • Cordoning off eight parking stalls in the central area of the visitor parking1
  • Inspection of site
  • Placement of a Prostar sandwich board in the central area of visitor parking with contact info
  • The installation of a porta-potty. This is locked, so if you had dreams of using an exotic new porta-potty, you will have to look elsewhere.
  1. Fun fact: I actually cordoned off many of the spots myself after getting permission from Prostar to move the pylons as needed. ↩︎