Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: Around 13–15°C, mostly sunny
Workers onsite: At least 3
I’ve been busy the past few days so I’m combining the work done on Friday and Saturday into one post.
Work done:
- Some more pavers installed in the parking lot
- Additional compacting of gravel in the area in front of the 240 building (Saturday)
- Some minor housekeeping (cleaning, organization)
It’s possible other work may have been done, but I did not observe anything specific.











