Phase 2 membrane project, Day 41–September 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23°C, cloudy, some clearing
Workers onsite: 6

Work done today:

  • Additional flashing applied to Building 244
  • More work on planter boxes at Building 244 entrance

Phase 2 membrane project, Day 40–September 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, sunny
Workers onsite: 2

Work done today:

  • Some work on reinstating the second planter at the Building 244 entrance

Phase 2 membrane project, Day 39–September 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 20°C, cloudy
Workers onsite: At least 5

Work done today:

  • Completion of and testing done on a mock-up to test aggregate (sand) under compaction
  • Additional work on reinstatement of one of the Building 244 planters
  • More work may have been done, but I could not directly observe any

Phase 2 membrane project, Day 38–September 3, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 20°C, cloudy
Workers onsite: At least 5

Work done today:

  • Further work on planters adjacent to Building 240 and 244.
  • A mock-up has been constructed, presumably for testing purposes.

Phase 2 membrane project, Day 37–September 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 20°C, cloudy with scattered showers late in the afternoon
Workers onsite: At least 5

Work done today:

  • Further work on reinstatement of the planter in the emergency repair area
  • Additional work may have been done, but if so, I may have missed it

Phase 2 membrane project, Day 36–September 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 22°C, partly sunny
Workers onsite: At least 9

Work done today:

  • Aeration (drainage) mat placed over most of the area adjacent to the 244 building
  • Small section of sealant applied near Building 240 entrance
  • Additional layer of membrane added between Building 240 and the emergency repair area
  • More flashing reinstated along patios of Building 244
  • Beginning of reinstatement of planter near emergency repair area