Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 19°C, mostly sunny
Workers onsite: At least 6
Work done today:
- Continued placement of pavers in the visitor parking lot adjacent to Building 244
