Phase 2 of the membrane project officially starts today, July 20, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

The City of New Westminster has finally granted the permit and today is the day when Phase 2 of the membrane replacement project officially gets underway.

I am not aware of any explanation from Prostar or Strata Engineering on why no work was done over the past week in either the Phase 1 extension area or the emergency repair area.

The notice provided to owners by Prostar outlining “Stage 3” is below.

Membrane work, June 30, 2026

Weather: 20°C, mostly cloudy
Workers onsite: Two observed

Work done today:

  • Additional installation of metal flashing was done on the 240 and 244 buildings and patios in the emergency repair area
  • General cleaning of the emergency repair area was done

Membrane work, June 29, 2026

Weather: 21°C, mostly cloudy
Workers onsite: At least two

Work done today:

  • Work was done on establishing pedestrian access through the emergency repair area (see photos below)
  • Additional work was done to complete pedestrian access in the Phase 1 extension area and to the stairs leading to the hospital lane.
  • General housekeeping (clean-up) was done, particularly in the emergency repair area
  • The biweekly meeting took place onsite with the following parties attending:
    • Strata Engineering
    • Prostar
    • Copperstone Council (represented by the President)
    • Quay Pacific did not have anyone in attendance

At the biweekly meeting, Prostar stated the pedestrian access noted above would be ready by the end of this week (Friday, July 3). From my observations, the access through the emergency repair area appears to be ready and all barriers/fencing have been removed.

There is also a reasonable expectation that the City of New Westminster will finally grant the permit for Phase 2 within the next few weeks.

Membrane work, June 23, 2026

Weather: 32°C, sunny
Workers onsite: 2

Work done today:

  • Additional pavers for the sidewalk added to the emergency repair area.
  • Some metal flashing (trim) has been restored to some patios.
  • Patio railings were re-instated (see photos and notes on this below).

Membrane work, June 22, 2026

Weather: 32°C, sunny
Workers onsite: At least 4

Work done today:

  • River stone/gravel was added to some of the emergency repair area.
  • Additional pavers/pedestals were placed on some patios.
  • Pavers were extended in the Phase 1 extension area in a way that doesn’t match the previous design–see photos below.

Membrane work, June 20, 2026

Weather: 23°C, sunny
Workers onsite: At least 4

Work done today:

  • Work today was focused on restoring pavers on patios in the emergency area. This work is nearly complete.