Sidewalk pavers re-instated in emergency repair area.
Many of the pavers on patios in the emergency area have been re-instated, with pedestals being used in place of what were previously wooden beams.
Some initial re-instatement of the parking lot pavers along the sidewalk in the Phase 1 extension.
Sidwewalk pavers returned to the emergency repair area.River stone/gravel will be used to fill inside the wooden beams, as before.Pedestals used to support some of the patios.Previously, wooden beams were used to support patios, as seen here.The first few parking lots pavers have been re-instated next to the sidewalk in the Phase 1 area.
Continued restoration of sidewalk pavers in Phase 1 area.
Start of full re-instatement of planter adjacent to the 248 building.
Cutting and placement of more wooden beams in the emergency repair area.
Sidewalk pavers being placed back in front of the 244 building.The 248 building planter being extended back to its original dimensions.Wooden beams cut and fitted into place adjacent to the 244 building.
Weather: 29°C, mostly cloudy Workers onsite: At least 4-6
Work done today:
Sand is being laid in the Phase 1 extension area. This is the final step before pavers are put back.
Aeration (drainage) mat and root barrier are being installed in the emergency repair area.
Additional work was done to address deficiencies and unfinished parts of the emergency area.
New wooden beams, part of the architectural detail, have been brought in for both areas.
In addition, the bi-weekly onsite meeting took place between all parties:
Strata Engineering
Prostar
Copperstone Council (represented by the President and Vice President)
Quay Pacific was not able to attend
Issues with site safety and storage were discussed and addressed. As part of this, all material on the easement facing Brunette Avenue has been removed.
Sand being spread in the Phase 1 extension area.Aeration mat placed in the emergency repair area.Some of the items that have since been cleared from the easement area facing Brunette Avenue.