Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 12°C, heavy rain with late clearing, clouds
Workers onsite: At least 5
Work done today:
- Concrete brick placed for the garden area adjacent to the Building 240 entrance and alongside initial part of the sidewalk on the north side of the Visitor Parking
- Additional compacting of gravel and placing of pavers around the 240 entrance
- Building 240 entrance re-opened, with temporary path to driveway