Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 16°C, mostly sunny
Workers onsite: At least 6
Work done today:
- Pavers placed along east side sidewalk by Building 240
- Drainage mat and initial gravel placed on membrane on the north side of the visitor parking
- Housekeeping (cleaning) of central courtyard and other areas in preparation for last stages of demolition
- Weekly meeting held between SE, Prostar, property management and council
- Further onsite meeting between SE, Prostar and council (represented by the president) to discuss and plan fixes for deficiencies and some misalignment issues