Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 17°C, mostly sunny
Workers onsite: At least 11
Work done today:
- Continued work on the sidewalk along the east edge of the parking lot
- More gravel has been moved into the area in the north end of the parking lot
- Some additional wooden beams have been cut to make them ready for placement
- More pavers are being moved into the completed area as demolition of the central courtyard begins



