Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny, high haze Workers onsite: None
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 27°C, sunny Workers onsite: At least five
Work done today:
Most of the remaining concrete slab of Stage 3 stripped and polished
Sealant applied to most of the same area (see photo below for exception)
Additional restoration of pavers to some patios
Sealant applied to recently stripped area adjacent to Building 240See explanatory text below.
In the photo above, you can where work was done to cut pavers. This requires the use of tools that use water to prevent overheating from the blade. The water flowed down onto the concrete slab (direction indicated by white arrow) and into the area circled in red, preventing them from finishing applying the sealant, as the area must be clean and dry. The circled area shows exposed concrete slab, with sealant to the left and membrane (previously applied) to the right. Why the workers chose to cut pavers so close to an active work area–which then compromised the work area–is a question left to the reader.
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 26°C, sunny Workers onsite: At least five
Work done today:
Pavers put back or partially restored on four patios
Membrane completed on four of the five Building 240 patios
Initial clearing of the last area on the south side of the parking lot, to allow for removal of old membrane
Partial paver restoration on Building 244 patios.Heavy machinery parked on new membrane. Clearing with excavator in the background.
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny Workers onsite: At least two
Work done today:
Additional work on patios by the 240 and 244 buildings