Phase 2 membrane project, Days 94 and 95–November 13/14, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 14°C, cloudy, showers
Workers onsite: 6–8

I’m combining these days because essentially the same work was done on both.

Work done on these days:

  • Spreading gravel/substrate material around the reinstated central courtyard perimeter.
Gravel placed around the reinstated Allan blocks forming the central courtyard, looking toward Building 244.

Phase 2 membrane project, Day 93–November 12, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 15°C, cloudy
Workers onsite: Around 6

Work done today:

  • The reinstatement of Allan blocks around the central courtyard was started
  • Blocks have been laid around the newly placed drainage mat to hold it in place pending the arrival of gravel/substrate material

Phase 2 membrane project, Day 92–November 10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, rain, heavy at times
Workers onsite: None observed

No work observed onsite today, possibly due to heavy rain.

It is possible work may have been done in the morning, but I was unable to observe any direct evidence.

Phase 2 membrane project, Day 91–November 9, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 13°C, mostly cloudy
Workers onsite: 6

Work done today:

  • Drainage mat installation begun on area with new membrane

Phase 2 membrane project, Day 88–November 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly cloudy, intermittent showers
Workers onsite: At least 8

Work done today:

  • Membrane applied around base of ventilation shed in central courtyard
  • Waterproofing material applied around base of fire hydrant
  • More second layer of membrane installed
  • Potential spots for new drains highlighted
  • Deficiencies in the membrane highlighted for repair and inspection