Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 15°C, cloudy
Workers onsite: Around 6
Work done today:
- The reinstatement of Allan blocks around the central courtyard was started
- Blocks have been laid around the newly placed drainage mat to hold it in place pending the arrival of gravel/substrate material