Phase 2 membrane project, Day 91–November 9, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 13°C, mostly cloudy
Workers onsite: 6

Work done today:

  • Drainage mat installation begun on area with new membrane

Leave a Comment