Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 14°C, cloudy, showers
Workers onsite: 6–8
I’m combining these days because essentially the same work was done on both.
Work done on these days:
- Spreading gravel/substrate material around the reinstated central courtyard perimeter.