Phase 2 membrane project, Days 94 and 95–November 13/14, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 14°C, cloudy, showers
Workers onsite: 6–8

I’m combining these days because essentially the same work was done on both.

Work done on these days:

  • Spreading gravel/substrate material around the reinstated central courtyard perimeter.
Gravel placed around the reinstated Allan blocks forming the central courtyard, looking toward Building 244.