Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny Workers onsite: At least two
Work done today:
Additional work on the patios around the 240 and 244 buildings
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 28°C, sunny Workers onsite: At least three
Work done today:
Two of the Building 240 patios had membrane applied
Sealant was applied to two other patios
The last patio has not been worked on yet
Membrane applied to two Building 240 patios.Sealant applied to two patios of Building 240. Not sure how water will get in by the doors, but now it’s safe!
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 29°C, sunny with some smoke haze Workers onsite: At least three
Work done today:
Additional work on some of the newly exposed patios at Building 240
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 29°C, sunny with smoke haze Workers onsite: At least seven
Work done today:
Completion of application of sealant and membrane in the recently cleared concrete slab adjacent to Building 244.
Closure of access to Allen Street, except via fire door in Building 240, to allow for further membrane installation.
Notes:
The closure of pedestrian access to Allen Street is expected to last one week, per Prostar. As the closure and notice of the closure were given the same day, it was not possible to get advance word out to owners and other residents.
View looking east.You shall not pass. For about one week.
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 29°C, sunny with smoke haze Workers onsite: At least seven
Work done today:
Sealant applied to most of the newly exposed concrete slab in the visitor parking adjacent to Building 244
Membrane installation continuing in the same general area
Initial work on the next set of patios, including removal of some Hardie planking
New sealant (foreground) and new membrane (background) in front of Building 244.Looking east across the same area.