Phase 2 membrane project, Day 83–October 30, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, cloudy, some light showers
Workers onsite: At least 6

Work done today:

  • Continued grinding/polishing of concrete slab to allow new membrane installation
  • Temporary shelter erected on completed area adjacent to Building 244 (I do not know its exact purpose)
  • Delivery of new membrane and sealant. This will be used to cover the last of the visitor parking lot.

Leave a Comment