Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 11°C, cloudy, some light showers
Workers onsite: At least 6
Work done today:
- Continued grinding/polishing of concrete slab to allow new membrane installation
- Temporary shelter erected on completed area adjacent to Building 244 (I do not know its exact purpose)
- Delivery of new membrane and sealant. This will be used to cover the last of the visitor parking lot.