Phase 2 membrane project, Day 99–November 19, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly sunny
Workers onsite: At least 6

Work done today:

  • Continued stripping of entrance area of Building 240 in preparation for application of sealant and membrane
  • Reinstatement of more pavers around the central courtyard
  • The first of two days coring new drains that will provide better overall drainage in the parking lot