Phase 2 membrane project, Day 8–July 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 22°C, mix of clouds and sun
Workers onsite: At least four

Work done today:

  • Further work on preparing the concrete slab in front of Building 244 for new membrane.
  • Sealant, membrane, and aeration (drainage) mats have arrived for the area.

Mind your garbage

Lately we’ve had two problems:

  • People overfilling the garbage bins in the 244 garbage room
  • People putting cardboard into the garbage bins

There are three garbage bins in the 244 garbage room. They are all directly beside each other. It is literally a few extra steps to go to the one farthest from the door. If the first bin (or any other) is full (garbage is past the top of the bin and is forming a “mound” on top), DO NOT USE THAT BIN. Use one of the other two bins.

Cardboard only goes in the bins that are marked specifically for Flattened Cardboard Only. These are past the regular garbage bins and are clearly marked.

When bins are overfull or cardboard is put in the wrong bin, Waste Management charges extra, a cost that is carried by all owners and is 100% unnecessary if people dispose of waste and cardboard properly.

Please do your part!

New signs have been added to the three garbage bins:

Membrane work, July 3, 2026

Weather: 22°C, sun and clouds
Workers onsite: At least five

Work done today:

  • River stone/gravel added in Phase 1 extension
  • Completion of reinstatement of pavers in Phase 1 extension
  • Additional placement of Allen blocks on planter adjacent to the 248 building
  • The pavers outside the fire door of the 240 building have been adjusted to allow the door to open properly

Membrane work, June 25, 2026

Weather: 20°C, cloudy
Workers onsite: At least 2

Work done today:

  • Soil placed in the Phase 1 extension, adjacent to the wooden beams, with additional soil placed into the planter adjacent to the 244 building.
  • Bridge placed in emergency repair area, possibly to allow foot traffic through as remainder of the area is worked on.
  • Flashing is being cut and put back into the base of the 244 building in the emergency repair area.

Membrane work, June 16, 2026

Weather: 24°C, sunny
Workers onsite: At least 4-6

Work done today:

  • Blue Drop installed irrigation piping in the emergency repair area.
  • Additional work on the emergency repair area to install aeration mat and placement of wooden beams.
  • Sidewalk from staircase and Allan blocks both extended in the Phase 1 extension.
  • Wooden beams placed in Phase 1 extension.

Membrane work, June 10, 2026

Weather: 18°C, mix of sun and clouds
Workers onsite: At least 4-6

Work done today:

  • Additional work on completing the membrane install in the emergency repair area
  • Substantial amount of root barrier and aeration mat laid down in the Phase 1 extension area