Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 28°C, sunny Workers onsite: At least five
Work done today:
Membrane applied to last area of Stage 3 in visitor parking next to Building 240
Membrane upturn work started along Building 240
Freshly applied membrane in last section of Stage 3 area of the visitor parking.
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: February 2027 (new, was December 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 22°C, mix of clouds and sun Workers onsite: At least four
Work done today:
Further work on preparing the concrete slab in front of Building 244 for new membrane.
Sealant, membrane, and aeration (drainage) mats have arrived for the area.
Looking east, with new material on the concrete slab next to Building 244.
People overfilling the garbage bins in the 244 garbage room
People putting cardboard into the garbage bins
There are three garbage bins in the 244 garbage room. They are all directly beside each other. It is literally a few extra steps to go to the one farthest from the door. If the first bin (or any other) is full (garbage is past the top of the bin and is forming a “mound” on top), DO NOT USE THAT BIN. Use one of the other two bins.
Cardboard only goes in the bins that are marked specifically for Flattened Cardboard Only. These are past the regular garbage bins and are clearly marked.
When bins are overfull or cardboard is put in the wrong bin, Waste Management charges extra, a cost that is carried by all owners and is 100% unnecessary if people dispose of waste and cardboard properly.
Please do your part!
New signs have been added to the three garbage bins:
Soil placed in the Phase 1 extension, adjacent to the wooden beams, with additional soil placed into the planter adjacent to the 244 building.
Bridge placed in emergency repair area, possibly to allow foot traffic through as remainder of the area is worked on.
Flashing is being cut and put back into the base of the 244 building in the emergency repair area.
This bridge will likely be opened up eventually for pedestrian use.Metal flashing applied to base of the 244 building.Soil added back alongside the 244 building.
Blue Drop installed irrigation piping in the emergency repair area.
Additional work on the emergency repair area to install aeration mat and placement of wooden beams.
Sidewalk from staircase and Allan blocks both extended in the Phase 1 extension.
Wooden beams placed in Phase 1 extension.
Irrigation piping in the emergency repair area.Wooden beams placed in Phase 1 extension area.The sidewalk from the staircase has been expanded out to its previous length.