Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 28°C, sunny
Workers onsite: At least five
Work done today:
- Membrane applied to last area of Stage 3 in visitor parking next to Building 240
- Membrane upturn work started along Building 240