Weather: 22°C, sun and clouds
Workers onsite: At least five
Work done today:
- River stone/gravel added in Phase 1 extension
- Completion of reinstatement of pavers in Phase 1 extension
- Additional placement of Allen blocks on planter adjacent to the 248 building
- The pavers outside the fire door of the 240 building have been adjusted to allow the door to open properly