Membrane work, June 19, 2026

Weather: 26°C, sunny
Workers onsite: At least 4-6

Work done today:

  • Sidewalk pavers re-instated in emergency repair area.
  • Many of the pavers on patios in the emergency area have been re-instated, with pedestals being used in place of what were previously wooden beams.
  • Some initial re-instatement of the parking lot pavers along the sidewalk in the Phase 1 extension.