Issues with mail delivery to Building 244

Council is aware of access issues affecting Building 244 for mail delivery. The mail carrier key is working with Building 240 and 248, but for some reason it has stopped working this past week in Building 244.

While the cause of the issue is investigated, please help out the mail carrier by letting her into the Building 244 lobby to deliver the mail. Mail delivery usually happens between 12–1 p.m. Monday through Friday.

Phase 2 membrane project, Day 32–August 26, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 25°C, mostly sunny
Workers onsite: At least four

Work done today:

  • Clearing of concrete slab adjacent to emergency repair area
  • Stripping of membrane from concrete slab next to Building 240

Phase 2 membrane project, Day 31–August 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 32°C, sun with smoke haze
Workers onsite: At least four

Work done today:

  • Continued clearing of new area in front of Building 240
  • Pavers restored to more Building 240 patios

Phase 2 membrane project, Day 30–August 23, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 26°C, sunny
Workers onsite: At least four

Work done today:

  • Additional pavers removed from area adjacent to Building 240
  • Pavers removed from area adjacent to emergency repair area
  • Trees removed from planters adjacent to Building 240
  • Trees and waste removed from site

Phase 2 membrane project, Day 29–August 22, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, cloudy, early morning showers
Workers onsite: At least three

Work done today:

  • Removal of the Allen blocks from another Building 240 planter
  • Expansion of paver removal from parking lot adjacent to Building 240
  • Additional finishing work on some Building 240 patios