Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 21°C, cloudy, early morning showers
Workers onsite: At least three
Work done today:
- Removal of the Allen blocks from another Building 240 planter
- Expansion of paver removal from parking lot adjacent to Building 240
- Additional finishing work on some Building 240 patios