Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 30°C, sunny
Workers onsite: At least three
Work done today:
- Full Visitor Parking closure put into effect:
- Temporary fencing extended to cover full parking lot
- A path has been made for people to enter and exit Building 240
- The Building 248 underground parking is unaffected
- Sidewalk pavers removed from Building 240
- Landscaping company Terra Firma, in addition to their regular work, removed the hedges along the driveway, which had been previously pulled out of the ground
- Some of the parking lot pavers adjacent are being removed now
- One of the two planters at the Building 240 entrance has had its Allen blocks removed
- Some additional work done to complete a few of the Building 240 patios