Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 25°C, mostly sunny
Workers onsite: At least four
Work done today:
- Clearing of concrete slab adjacent to emergency repair area
- Stripping of membrane from concrete slab next to Building 240