See PDF below. To facilitate coring of new drains and cleaning of existing drains, Prostar is advising owners to remove vehicles from the stalls listed below between 8 am and 5 pm this Thursday and Friday.
Stan
Phase 2 membrane project, Day 96–November 16, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 12°C, clouds and some sun
Workers onsite: 6–8
Work done today:
- More gravel/substrate was spread around the central courtyard; additional gravel was also delivered
- Compacting of the substrate in the same area began
- After an onsite meeting, the corners of the central courtyard were pulled in tighter, to reduce vehicles colliding with the Allan blocks
- Blue Drop worked on the irrigation through the central courtyard, which will be routed more efficiently than before
- Housekeeping saw a large volume of garbage/waste material removed from the site



Phase 2 membrane project, Days 94 and 95–November 13/14, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 14°C, cloudy, showers
Workers onsite: 6–8
I’m combining these days because essentially the same work was done on both.
Work done on these days:
- Spreading gravel/substrate material around the reinstated central courtyard perimeter.


Phase 2 membrane project, Day 93–November 12, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 15°C, cloudy
Workers onsite: Around 6
Work done today:
- The reinstatement of Allan blocks around the central courtyard was started
- Blocks have been laid around the newly placed drainage mat to hold it in place pending the arrival of gravel/substrate material

Phase 2 membrane project, Day 92–November 10, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 12°C, rain, heavy at times
Workers onsite: None observed
No work observed onsite today, possibly due to heavy rain.
It is possible work may have been done in the morning, but I was unable to observe any direct evidence.

Phase 2 membrane project, Day 91–November 9, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 13°C, mostly cloudy
Workers onsite: 6
Work done today:
- Drainage mat installation begun on area with new membrane