Phase 2 membrane project, Day 10–July 30, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Further expansion of the Stage 3 area, demolition of more of the south side of the visitor parking lot adjacent to the 244 building

Phase 2 membrane project, Day 9–July 29, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Kryton (concrete-like) material applied to cracks in concrete slab adjacent to Building 244
  • Initial sealant and membrane applied to some areas of the slab

Phase 2 membrane project, Day 8–July 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 22°C, mix of clouds and sun
Workers onsite: At least four

Work done today:

  • Further work on preparing the concrete slab in front of Building 244 for new membrane.
  • Sealant, membrane, and aeration (drainage) mats have arrived for the area.

Phase 2 membrane project, Day 7–July 27, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 22°C, mostly cloudy
Workers onsite: At least four

Work done today:

  • Concrete slab adjacent to Building 244 further stripped and polished

Phase 2 membrane project, Day 6–July 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 18°C, mostly cloudy
Workers onsite: At least five

Work done today:

  • Completion of stripping membrane in front of Building 244
  • Concrete slab in same area polished in preparation for new membrane
  • Area now connects to the work in the emergency repair area

Phase 2 membrane project, Day 5–July 24, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 27°C, sunny
Workers onsite: At least five

Work done today:

  • Stripping of membrane and polishing of concrete slab in area of visitor parking in front of Building 244 began