Phase 2 membrane project, Day 6–July 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 18°C, mostly cloudy
Workers onsite: At least five

Work done today:

  • Completion of stripping membrane in front of Building 244
  • Concrete slab in same area polished in preparation for new membrane
  • Area now connects to the work in the emergency repair area