Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 27°C, sunny
Workers onsite: At least five
Work done today:
- Stripping of membrane and polishing of concrete slab in area of visitor parking in front of Building 244 began