Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 23°C, sunny
Workers onsite: At least four
Work done today:
- Further expansion of the Stage 3 area, demolition of more of the south side of the visitor parking lot adjacent to the 244 building