Phase 2 membrane project, Day 38–September 3, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, cloudy
Workers onsite: At least 5

Work done today:

  • Further work on planters adjacent to Building 240 and 244.
  • A mock-up has been constructed, presumably for testing purposes.

Phase 2 membrane project, Day 37–September 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, cloudy with scattered showers late in the afternoon
Workers onsite: At least 5

Work done today:

  • Further work on reinstatement of the planter in the emergency repair area
  • Additional work may have been done, but if so, I may have missed it

Phase 2 membrane project, Day 36–September 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 22°C, partly sunny
Workers onsite: At least 9

Work done today:

  • Aeration (drainage) mat placed over most of the area adjacent to the 244 building
  • Small section of sealant applied near Building 240 entrance
  • Additional layer of membrane added between Building 240 and the emergency repair area
  • More flashing reinstated along patios of Building 244
  • Beginning of reinstatement of planter near emergency repair area

Phase 2 membrane project, Day 35–August 31, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 24°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Flashing restored on some patios on both Building 240 and 244
  • Second layer of membrane applied to area adjacent to Building 240
  • Sealant work finished near emergency repair area and first layer of membrane applied
  • Additional signage posted throughout area by Prostar

Phase 2 membrane project, Day 34–August 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, cloudy, some sun
Workers onsite: At least four

Work done today:

  • Sealant applied to newly exposed concrete slab areas by Building 244
  • Membrane applied to one of the two above areas
  • Prostar has placed two sandwich boards noting no visitor parking