Phase 2 membrane project, Day 44–September 11, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, partly sunny
Workers onsite: 6

Work done today:

  • Cleaning pavers (bricks). Yes, again.

Phase 2 membrane project, Day 43–September 10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, partly sunny
Workers onsite: 6

Work done today:

  • Pavers (bricks) cleaned
  • No other work observed

Phase 2 membrane project, Day 42–September 9, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, partly cloudy
Workers onsite: 6

Work done today:

  • Pavers (bricks) cleaned
  • No other work observed

(No photos today.)

Phase 2 membrane project, Day 41–September 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, cloudy, some clearing
Workers onsite: 6

Work done today:

  • Additional flashing applied to Building 244
  • More work on planter boxes at Building 244 entrance

Phase 2 membrane project, Day 40–September 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 25°C, sunny
Workers onsite: 2

Work done today:

  • Some work on reinstating the second planter at the Building 244 entrance

Phase 2 membrane project, Day 39–September 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, cloudy
Workers onsite: At least 5

Work done today:

  • Completion of and testing done on a mock-up to test aggregate (sand) under compaction
  • Additional work on reinstatement of one of the Building 244 planters
  • More work may have been done, but I could not directly observe any