Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 24°C, mostly sunny
Workers onsite: At least 8
Work done today:
- Flashing restored on some patios on both Building 240 and 244
- Second layer of membrane applied to area adjacent to Building 240
- Sealant work finished near emergency repair area and first layer of membrane applied
- Additional signage posted throughout area by Prostar