Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 21°C, cloudy, scattered showers
Workers onsite: At least two
Work done today:
- Further scraping and cleaning of the concrete slab in front of Building 240
- The porta-potty was moved from the central courtyard