Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 10°C, Light showers and clouds
Workers onsite: At least 6
Work done today:
- Old drainage mat and membrane removed from central courtyard area
- Pavers adjacent to Building 240 used for temporary pedestrian access have been removed
- The temporary bridge from the Building 240 entrance to the driveway is now open
- A smaller temporary bridge is in place by Building 244 now, but not yet open
As of today, the majority of the visitor parking lot area has either been demolished or reinstated.


