Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 15°C, sunny
Workers onsite: At least 6
Work done today:
- More demolition of the central courtyard, including removal of most dirt
- Initial work on temporary access path from the Building 240 entrance. This will allow workers to demolish the remaining area of the visitor parking lot.