Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 14°C, mostly cloudy
Workers onsite: At least 6
Work done today:
- More demolition of the central courtyard area
- Polymer binding material added over Phase 1 extension pavers. This is a sand-like material that fits between pavers and forms a concrete-like seal to hold pavers in place.