Phase 1 Membrane Project, Day 103 (January 8, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 5C, cloudy

Work done today:

  • Continued work on cutting and placing the wooden beams around the base of the 244 building.
  • Workers onsite: At least two.

Phase 1 Membrane Project, Day 102 (January 7, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 4C, clouds and light rain

Work done today:

  • The start of cutting and placement of the wooden beams that will form a perimeter around the back (west) and north side of the 244 building. The area between the beams and the building will be filled with gravel, as it was prior to construction.
  • Workers onsite today: At least four.

New styrofoam bin in the garbage room

It’s not the most exciting news in the world, but there is now a bin in the 244 garbage room for styrofoam. Currently it’s best to keep the lid closed, because the lid is the only part where it states it is for styrofoam. Better signage will be provided soon.

Please don’t put styrofoam in any other bin, including the dumpsters, as we get charged extra for its removal.

As a reminder, there are also two glass-only bins in the garbage room. More signage will be provided for these soon, but in the meantime, keep the lid on one bin down, so people can see they are meant for glass only.

Finally, when I was in the garbage room today, I noticed the dumpster for flattened cardboard only was full of…everything, including:

  • writing paper
  • packing paper
  • wrapping paper
  • paper bags
  • envelopes
  • cup and bottles
  • bags of garbage, like McDonald’s delivery bags full of dirty napkins, cups, etc.

I spent some time moving items to the garbage, containers and mixed paper bins, but PLEASE do not put anything but flattened cardboard into this dumpster. The front is clearly labelled flattened cardboard only, and we have plenty of other bins for all appropriate items–use them! If the cardboard dumpster keeps getting misused, we may again incur extra costs.

Take the time to dispose of your recycling and garbage properly–everyone benefits!

Phase 1 Membrane Project, Day 101 (January 6, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, showers

Work done today:

  • More work on the metal flashing around the base of the 244 building
  • Additional work may have been done, but is not visible
  • Workers onsite: At least two

Phase 1 Membrane Project, Day 100 (January 5, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, clouds, some sun

Work done today:

  • More work on installing the metal flashing along the base of the 244 building
  • Workers onsite: At least two
  • Strata Engineering was also onsite for inspection