Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 8C, rain and drizzle
Work done today:
- Continued placement and work on Allan blocks between the 244 and 248 buildings
- Clean-up of open area at edge of the visitor parking
- Construction of temporary path over open area, to allow re-opening of sidewalk and stairs
- Raking/levelling of the topsoil in all areas
- Work on crack repairs in the underground parkade
- Workers onsite: At least five
- Strata Engineering was also onsite for inspection of current work