Phase 1 Membrane Project, Day 123 (February 2, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, rain and drizzle

Work done today:

  • Continued placement and work on Allan blocks between the 244 and 248 buildings
  • Clean-up of open area at edge of the visitor parking
  • Construction of temporary path over open area, to allow re-opening of sidewalk and stairs
  • Raking/levelling of the topsoil in all areas
  • Work on crack repairs in the underground parkade
  • Workers onsite: At least five
  • Strata Engineering was also onsite for inspection of current work

Leave a Comment