Phase 2 membrane project, Day 13–August 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven

Work done today:

  • Sealant applied to most of the newly exposed concrete slab in the visitor parking adjacent to Building 244
  • Membrane installation continuing in the same general area
  • Initial work on the next set of patios, including removal of some Hardie planking

Phase 2 membrane project, Day 12–August 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, cloudy, some sun, early morning showers
Workers onsite: At least three

Work done today:

  • Further stripping and cleaning of the exposed concrete slab in the parking lot

Phase 2 membrane project, Day 11–July 31, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 27°C, sunny
Workers onsite: At least five

Work done today:

  • Membrane applied to most of the newly cleared concrete slab in front of Building 244.
  • Upturns (membrane) applied to remainder of the base along the 244 building.
  • Further demolition of the visitor parking, now encompassing about half of the parking lot.

Phase 2 membrane project, Day 10–July 30, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Further expansion of the Stage 3 area, demolition of more of the south side of the visitor parking lot adjacent to the 244 building

Phase 2 membrane project, Day 9–July 29, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Kryton (concrete-like) material applied to cracks in concrete slab adjacent to Building 244
  • Initial sealant and membrane applied to some areas of the slab

Phase 2 membrane project, Day 8–July 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 22°C, mix of clouds and sun
Workers onsite: At least four

Work done today:

  • Further work on preparing the concrete slab in front of Building 244 for new membrane.
  • Sealant, membrane, and aeration (drainage) mats have arrived for the area.