Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy
Work done today:
Continued work on installing membrane on the five affected patios.
Application of primary to the majority of the concrete slab between the 244 and 248 buildings.
Primer applied to most of the concrete slab, done today.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 11C, drizzle and light rain
No work onsite today.
Biweekly onsite meeting took place with:
Strata Engineering
Prostar
Copperstone Council, represented by the Vice President
Quay Pacific had no representation this week due to illness
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, clouds and rain, at time heavy
Work done today:
Continued work on applying primer and laying down membrane on the five affected patios on Building 244.
Workers onsite: At least two.
Our patio with primer applied. Cracks have not been repaired.Patio with membrane being laid down.
The following shot is of a crack repair behind the 244 building. While the concrete curb and other crack repairs were covered with plastic for several days after the work was done, this crack was left exposed. This shot, taken on November 14, shows how the crack is both partially submerged under standing water and how the Krten Krystol mixture is starting to flake off.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 12C, Heavy rain at times, clouds
Work done today:
Work on the application of primer and membrane on patios has begun.
Workers onsite: At least three.
Strata Engineering also appeared to be onsite in the morning.
Other work may have been done, but I can’t confirm.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 10C, clouds and showers
Work done today:
Additional repair work on leaks
Delivery of two large propane tanks
Delivery of at least five large cans of liquid material (possibly primer)
Workers on site: At least 3
Site viewed from hospital path, November 12, 2025, crack repairs visible.