Phase 1 Membrane Project, Day 16 (September 17, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 24C, hazy sun

Work done today:

  • Highmark Plumbing continued work on the three new drains, completing grouting and plumbing on the drains topside

Phase 1 Membrane Project, Day 14 (September 15, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, mostly sunny

Work done today:

  • A plumbing company and other workers spent time working on the new drains that were drilled, along with the piping underneath in the underground parking lot.

The garbage room should smell a little nicer now

Not because we went around inside it spraying Febreze, but the vents that allow air in and out have been hosed down, allowing air to flow more freely. For good measure, the floor was hosed down, too.

Signs have been placed on the three dumpsters in the 244 garbage room, reminding the garbage removal company to fold the lids back when returning them to the garbage room. We’ll continue to monitor and follow up with the company if needed to make sure the bins remain easily accessible.