Phase 1 Membrane Project, Day 58 (November 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, mix of rain and cloud

Work done:

  • Wooden forms removed from concrete curb.
  • Plastic sheets removed from crack repairs on the concrete slab.
  • Workers onsite: At least two.

Also:

  • Delivery of multiple shrink-wrapped palettes. I’m unsure of the contents, but it is possible it is membrane material, as installation of the new membrane is close now.
  • Strata Engineering had people inspecting the site.

Phase 1 Membrane Project, Day 57 (November 6, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, intermittent heavy rain throughout day

Work done today:

  • Unsure what was done, but Prostar was onsite.
  • Strata Engineering was inspecting the site early in the morning.
  • Workers onsite: Unknown.

Phase 1 Membrane Project, Day 56 (November 5, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, rain

Work done today:

  • Plastic covering placed over most of the crack repairs on the concrete slab
  • Other work may have been done, but unable to confirm as of this writing; will update if more details become known
  • Workers onsite: At least two

Phase 1 Membrane Project, Day 55 (November 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, mostly clear.

Work done today:

  • Concrete curb was poured along the base of the retaining wall and covered with plastic in anticipation of rain.
  • Miscellaneous cleaning of the work area.
  • Workers onsite: At least four, possibly more.

Phase 1 Membrane Project, Day 54 (November 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, high cloud and filtered sun

The fifth biweekly status meeting took place mid-morning. Attending were:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council, represented by the Vice President

Work done today:

  • Continued work on repairing cracks on the concrete slab using Kyrton grout material
  • Workers onsite: At least two observed