Phase 2 membrane project, Day 29–August 22, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, cloudy, early morning showers
Workers onsite: At least three

Work done today:

  • Removal of the Allen blocks from another Building 240 planter
  • Expansion of paver removal from parking lot adjacent to Building 240
  • Additional finishing work on some Building 240 patios