Phase 2 membrane project, Day 28–August 21, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 30°C, sunny
Workers onsite: At least three

Work done today:

  • Full Visitor Parking closure put into effect:
    • Temporary fencing extended to cover full parking lot
    • A path has been made for people to enter and exit Building 240
    • The Building 248 underground parking is unaffected
  • Sidewalk pavers removed from Building 240
  • Landscaping company Terra Firma, in addition to their regular work, removed the hedges along the driveway, which had been previously pulled out of the ground
  • Some of the parking lot pavers adjacent are being removed now
  • One of the two planters at the Building 240 entrance has had its Allen blocks removed
  • Some additional work done to complete a few of the Building 240 patios