Emergency membrane repair/Phase 1 completion (pre-Phase 2 work), Day 6

Weather: 22°C, partly sunny
Workers onsite: At least six

Work done today:

  • Phase 1 final area was further cleared today
  • The planter on the right side of the 244 building entrance and its tree were removed
  • Pavers were removed from much of the area and have now been stacked temporarily in the central courtyard on pallets
  • The parking curbs in the area have been removed and temporarily stacked in a planter from earlier Phase 1 work, between the 244 and 248 buildings

As of Saturday, May 9th:

  • Access to the stairs leading to the hospital pathway remains OPEN. This could change when work resumes on Monday.
  • The fire exit door from the 244 building is now clear (but still inside the construction area)
  • The fire exit door on the 240 building still has a large drop-off.
  • The emergency repair area remains CLOSED to pedestrian access.
  • Visitor parking currently:
    • 21 stalls available, including two accessible
    • 16 stalls unavailable, including one accessible