Weather: 22°C, partly sunny
Workers onsite: At least six
Work done today:
- Phase 1 final area was further cleared today
- The planter on the right side of the 244 building entrance and its tree were removed
- Pavers were removed from much of the area and have now been stacked temporarily in the central courtyard on pallets
- The parking curbs in the area have been removed and temporarily stacked in a planter from earlier Phase 1 work, between the 244 and 248 buildings
As of Saturday, May 9th:
- Access to the stairs leading to the hospital pathway remains OPEN. This could change when work resumes on Monday.
- The fire exit door from the 244 building is now clear (but still inside the construction area)
- The fire exit door on the 240 building still has a large drop-off.
- The emergency repair area remains CLOSED to pedestrian access.
- Visitor parking currently:
- 21 stalls available, including two accessible
- 16 stalls unavailable, including one accessible