Emergency membrane repair (pre-Phase 2 work), Day 5

Weather: 19°C, cloudy
Workers onsite: At least five

Work done today:

  • Temporary fencing has been put in place for the completion of Phase 1 work in front of the 244 building
  • Removal of paver stones has begun in the affected area
  • The C can (office/storage) has been moved from the central courtyard next to the 248 building. It will remain there until Phase 2 is completed.

Other items:

  • Membrane and sealant has been delivered

Some issues of concern have been found and council is following up on these. These include:

  • Inadequate access from the 244 fire exit in case of emergency (see photo below)
  • Inadequate access from the 240 fire exit in case of emergency (see photo below)
  • Removed irrigation piping not cleared from property