Weather: 19°C, cloudy
Workers onsite: At least five
Work done today:
- Temporary fencing has been put in place for the completion of Phase 1 work in front of the 244 building
- Removal of paver stones has begun in the affected area
- The C can (office/storage) has been moved from the central courtyard next to the 248 building. It will remain there until Phase 2 is completed.
Other items:
- Membrane and sealant has been delivered
Some issues of concern have been found and council is following up on these. These include:
- Inadequate access from the 244 fire exit in case of emergency (see photo below)
- Inadequate access from the 240 fire exit in case of emergency (see photo below)
- Removed irrigation piping not cleared from property