Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 10°C, cloudy, intermittent showers
Workers onsite: At least 3
Work done today:
- Water mitigation to reduce water leaking into underground parking
- Polishing of recently exposed concrete slab to prepare it for sealant and new membrane