Phase 2 membrane project, Day 82–October 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 9°C, cloudy, intermittent showers
Workers onsite: At least 2

Work done today:

  • Further stripping of old membrane from newly exposed areas
  • I observed Strata Engineering onsite. A trench was dug near the Phase 1 extension area, likely to investigate the material below where pavers were sinking