Phase 2 membrane project, Day 81–October 27, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, showers and clouds
Workers onsite: At least 2

Work done today:

  • The Terminator, a machine that strips membrane and sealant, was used to expose the concrete slab in the central courtyard area and out beyond toward Building 240

Also of note: With the combination of old membrane and sealant being removed and rainy weather, there will be more leaks in the underground parking. If you see an issue of concern, report it to Council: copperstonecouncil@fastmail.com

Leave a Comment